Aberedw
Aberedw
Promoter: Bute Energy
Details: capacity 120 MW 18 Turbines 3 km East of Builth Wells
Timeline:
Winter 2023: current phase. Non-statutory consultation with communities, stakeholders and consultees 6 weeks
Winter 2023 - autumn 2024: Evaluating and considering feedback received to progress the project design
Summer 2024: Meteorological Mast Installation (nb, this assumes planning permission, not mentioned.)
Throughout 2024: Design development, EIA and reporting
Spring 2025: Statutory pre-application consultation with communities, stakeholders and consultees
Summer 2025: Statutory consulation
Autumn 2025: Submission of DNS application
Comments: A beautiful upland area set in pastoral countryside and dominating Builth Wells and the river Wye. Aberedw Common is owned by the Legge Bourke family which is keen to sell the land but a number of graziers have traditional common land rights to the unenclosed hill